A dispute in the Party Wall sense of the word need not be much of a dispute at all; even if the Act says it is. Under the Party Wall etc. Act 1996, if an adjoining owner doesn’t consent within 14 days of receiving notice of the proposed works then the parties are deemed to be “in dispute”. The way that disputes under the Act are resolved is by each of the owners appointing a surveyor and those surveyors agreeing the terms of Party Wall Agreement.
Even if the adjoining owner decides to concur with their neighbour’s choice of surveyor as “agreed surveyor” (normally a good decision for minor works) there is still a “dispute” to be resolved so an award must be drawn up and served on the owners.
In effect, what an adjoining owner is saying when they instigate a dispute is that they would like to have their interests protected by a person who understands construction matters and is familiar with the procedures under the Party Wall Act.
It could not be easier for an adjoining owner to instigate a dispute; they need do nothing at all. If Party Wall Notices and Notices of Adjacent Excavation are not consented within 14 days of being received then a DISPUTE has arisen.
The adjoining owner may appoint a surveyor (or concur in the appointment of an agreed surveyor) within the 14 day period but they needn’t rush their decision. Once the 14 days have elapsed they must be sent a follow-up letter asking them to appoint a Party Wall Surveyor within 10 days or risk one being appointed on their behalf by the building owner (the party planning the work). If a building owner does gain the right to appoint a surveyor on behalf of their neighbour that cannot be the same surveyor that they are using; an Agreed Surveyor cannot be appointed unless both owners confirm that appointment in writing.
Once a dispute has arisen both the building owner and the adjoining owner change from being “clients” to “appointing owners” - the terminology reinforces the surveyor’s duty to be impartial. A surveyor can serve notice on behalf of their client because at that stage it is not known whether the adjoining owner will consent or not. If they consent there will be no award and no need for a party wall surveyor.
[edit] Related articles on Designing Buildings Wiki
- 10(4) Party Wall Surveyor Appointments.
- Adjoining buildings definition.
- Adjoining owner.
- Fence.
- Institute of party wall surveyors.
- Line of junction notice.
- Party structure notice.
- Party Wall Act.
- Party wall surveyor.
- Preventing wall collapse.
- Responsibility for boundary features.
- Right of support.
- Trespass.
- Wall types.
- What approvals are needed before construction begins.
- Who Pays for Party Wall Surveyor's Fees?
Featured articles and news
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.
The changed R&D tax landscape for Architects
Specialist gives a recap on tax changes for Research and Development, via the ACA newsletter.
Structured product data as a competitive advantage
NBS explain why accessible product data that works across digital systems is key.
Welsh retrofit workforce assessment
Welsh Government report confirms Wales faces major electrical skills shortage, warns ECA.
A now architectural practice looks back at its concept project for a sustainable oceanic settlement 25 years on.
Copyright and Artificial Intelligence
Government report and back track on copyright opt out for AI training but no clear preferred alternative as yet.
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
Inspiration for a new 2026 wave of Irish construction professionals.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.